|
Cira Takes Centre Stage
Cira Centre adds a new look to
Philadelphia's skyline
By Harris M. Steinberg, AIA
Philadelphia is witnessing the addition of the first new
skyscraper to its skyline in more than a decade with the
development of the 28-story Cira Centre. The design and
construction teams are addressing significant challenges
to make the 727,000-sq.-ft. office tower above neighboring
30th Street Station a reality.
|
|
|
Cira Centre required 7,200 tons of
project steel, including a 36-ton column designed to
accommodate 1,600 lbs. per ft.
|
A new icon is emerging above the western bank of the Schuylkill
River in Philadelphia.
The 28-story Cira Centre office tower, designed by internationally
renowned Cesar Pelli & Associates Architects of New Haven,
Conn., is the first new skyscraper to rise above the city
in more than a decade, adding a dramatic element to the Philadelphia
skyline and drawing attention to the neighboring University
City area.
Brandywine Realty Trust is developing the 727,000-sq.-ft.
tower alongside 30th Street Station, Amtrak's second-busiest
station in the United States with 2.5 million rail commuters
passing through it each year. Cira Centre will also tower
above the nearby campuses of the University of Pennsylvania
and Drexel University.
With little obstruction from surrounding structures, Cira
Centre will have a commanding presence in the neighborhood.
Contrasting with the Beaux-Arts limestone solemnity of 30th
Street Station, the new tower, sheathed in a structurally
glazed customized curtain wall system, will be visible from
360 degrees.
"[The multifaceted structure] is interesting on all
sides - its crystalline form allowing the different facades
to be transformed [visually] by the taut glass skin throughout
the day and year," said Mark Shoemaker, AIA, associate
principal of Cesar Pelli & Associates and the design team
leader.
Brandywine sought to create a building that was "practical
and workable" on a difficult site, said Jeffrey R. Weinstein,
the firm's vice president for construction. The company selected
the one portion of the site without any active rail lines
or other physical impediments, but it still presented obstacles
to the design and construction team.
"The biggest challenge that the team faced was building
a multistory high-rise on a postage stamp site bounded on
three sides," said Richard Treglown, project manager
for Turner Construction of Philadelphia. Treglown is a veteran
of four Philadelphia office towers and the recently completed
Lincoln Financial Field for the Philadelphia Eagles.
A tight site
|
|
|
The Cesar Pelli design, pictured in
this rendering, is a multifaceted structure with a crystalline
form.
|
Access to the tight site is limited to Arch Street on the
southern side. An existing parking deck, which couldn't take
additional structural loads, borders to the east. A parking
garage was recently completed to the north, and the freight
lines of Penn Coach Yards on the west side couldn't have service
interruptions.
To further complicate matters, Arch Street, built on a deck
above the floodplain, is a Pennsylvania state highway that
handles significant volume of traffic exiting and entering
Interstate 76 at 30th Street Station.
Site constrictions forced demolition to occur within 15 ft.
of a highly sensitive 25,000-volt electrical line - the catenary
for the freight line electrical power. On the east, adjacent
to Amtrak's Northeast Corridor high-speed rail line, tying
in a storm drainage line required coordination with Amtrak
to ensure that service was not disrupted on the busy rail
corridor.
Weinstein said his development team meets with Amtrak representatives
weekly and there is good cooperation and coordination with
the rail service provider. Deliveries to the basement-level
loading dock have to be scheduled with an Amtrak flagman so
that the delivery trucks can cross the freight lines without
interrupting service.
Without layout or storage space onsite, all deliveries are
staged on Arch Street between 9:30 a.m. and 4:30 p.m. so as
not to disrupt rush-hour traffic. Everything is lifted off
trucks in front of the building and hoisted up and installed.
No materials will be stored on site until the building is
closed in and sealed.
The building sits on a deck located 20 ft. above track level,
which meant tying into utility mains beneath Market Street
one block to the south. Luckily, the architects of 30th Street
Station included room-sized subterranean tunnels stretching
along all sides of the block-long building.
Used originally for mail transfer from railcars to the main
post office building at 30th and Market streets, these now-abandoned
tunnels proved the prefect conduit for water, gas, sanitary,
electrical and telephone lines.
Massive steel
|
|
|
Construction required significant
coordination with Amtrak and the site's other neighbors.
|
The need to create clear-span floor plates for office tenants
required a structural steel frame with massive transfer girders
- some between 32 and 42 ft. long. The frame rests on 34,
50-ft.-deep caissons that Treglown said average between 6
and 8 ft. in diameter.
The 7,200 tons of project steel includes what Treglown said
is the biggest steel he has ever seen. For example, he highlighted
a 36-ton column designed to accommodate 1,600 lbs. per ft.
Timing is everything on a fast-track construction project
such as this, and steel was purchased just as the U.S. Army
was requiring 1- and 2-in.-thick steel plate to reinforce
Humvees in Iraq. That impacted the supply of steel for the
perimeter columns and initially set the project back seven
weeks.
|
|
|
The Cira Centre was topped out in
November and is on track for completion in the fall.
|
But Treglown said Canam, a Canadian steel supplier, worked
with the building's structural engineers, Ingenium of Houston,
Texas, to overcome initial delays and lost time was made up
in 2.5 months.
All involved with the project credit the excellent working
relationships between the team members as a key component
of the project's success to date.
"There are no rigid and formalized relationships between
the players," said Malcolm Quinion, RIBA, project manager
for Bower Lewis Thrower Architects of Philadelphia, the project's
executive architect. "Rather, everyone gets down to issues
and works together and contributes to solutions."
The Cira Centre project is on track to be completed in the
fall.
Harris M. Steinberg, AIA, is the executive
director of Penn Praxis of the School of Design of the University
of Pennsylvania.
Waking Up the Neighborhood
|