|
Out with a Bang
Old Washington Convention Center
imploded
By Bruce Buckley
In the first implosion attempted in the District in nearly
30 years, the 800,000-sq.-ft. Washington Convention Center
was taken down in a matter of seconds.
|
The implosion
sequence began at 7:30 a.m. (left) in the concrete columns
between Hall A and Hall B. The implosion moved outward
to other portions of the structure (middle) with firings
separated by milliseconds. The sequence ended after
12 seconds of firings (right) and the walls began to
fold on top of the fallen structure.
|
After hosting more than 1,500 major conventions during its
20-year existence, the old Washington Convention Center went
out with a bang Dec. 18.
In a spectacle that brought down the house, the 800,000-sq.-ft.
structure was imploded - the first such demolition attempted
in the District in nearly 30 years.
At a project cost of $6.7 million, the implosion not only
saved the Washington Convention Center Authority nearly $1
million compared to conventional demolition methods, it also
mitigated onsite risks, said Terry Anderson, executive vice
president of Wrecking Corp. of America in Alexandria, Va.
"It was safer in terms of not having to put employees
up there to do high steel burning," Anderson said. "This
way, our guys can do all the work within the safety of an
excavator."
Goel Construction Services of Washington, D.C., was the general
contractor on the project; Wrecking Corp. served as the demolition
contractor; and Demolition Dynamics of Cincinnati, Ohio, was
the implosion contractor.
The convention center covers nearly four city blocks, bordered
by Ninth St. NW, 11 St. NW, H St. NW and New York Ave. City
officials and neighboring business owners watched the implosion
from across Mt. Vernon Square inside the new Washington Convention
Center, which opened in 2003.
Tough sell
While the implosion saved the WCCA some money, it didn't
save it much time. Getting the proper permits and approvals
was no easy task in a city that hadn't allowed an implosion
since a 10-story parking garage was brought down in 1974.
In addition to working with the city, the team had to allay
the concerns of the convention center's neighbors, including
the U.S. Secret Service, the U.S. Mint and two major hotels.
"We're in a post Sept. 11 era here, and to take a process
that most people aren't familiar with or have only been exposed
to via Vegas-style implosions on the Learning Channel, and
say that we are going to do this in the city's central business
district, that doesn't sit well with some people," Anderson
said.
After nearly three months of negotiations, all permits were
finalized in mid-November and the team began to prepare the
site for implosion. Part of the preparation included gutting
as much material from inside the convention center as possible
to reduce the levels of dust that could be produced by the
implosion.
Schedules were tight because of the extensive coordination
required with city agencies. The Dec. 18 date was chosen so
the event wouldn't conflict with the holidays or the presidential
inauguration ceremonies.
Meanwhile, the team fine-tuned the implosion sequence to
figure out how to bring down a large structure packed with
heavy steel without damaging neighboring structures. The convention
center was built as three two-level structures - Halls A,
B and C. The lower level featured concrete framing of about
20 ft. in height, which supported a waffle-pan deck with 250-
to 400-lb. loads.
The next level was a steel-truss roof system. Hall A was
one of the most daunting challenges because of its veriendeel
roof with open spans of 250 to 270 ft. The flanges on that
steel were up to 4 in. thick, Anderson said.
"This is some of the heaviest stuff that's ever been
shot with shape charges," Anderson said.
The main goal was to drop the steel-truss roof so that it
would lie on the concrete slab below and be removed later
by excavators, Anderson said.
Ready, aim, fire
The 12-second-long implosion sequence included 400 separate
delays set milliseconds apart from each other. During that
time, nearly 500 columns set with explosives were shot out,
bringing the entire building down like a carefully choreographed
domino display.
"You don't want the entire building hitting the ground
at once," Anderson said. "The idea is to get one
part of the building moving first, then radiate out from there."
The initial blasts began between Hall A and Hall B then moved
outward, leaving Hall C as the last to go. Concrete columns,
which had been drilled out and filled with a nitroglycerine-based
explosive, were shot out first to bring down the floor. By
doing so, Anderson said it creates a mattress effect for the
upper steel columns to land on.
Milliseconds later, shape charges sliced the steel columns.
Shape charges are used specifically for cutting steel in half.
They were originally designed by NASA to cut away the metal
stages of early rockets during takeoff sequences.
Kicker charges, set on the side of the steel, pushed apart
the split columns so they would collapse. As the steel fell,
so did the roof, then the walls folded in toward the center
of the structure. Anderson said the team attached .75-in.
steel cables between the walls and floors at a 45-degree angle
to ensure that the walls would fold inward and not out.
Within seconds of the final charge, the last pieces of the
old convention center fell to earth. All combined, the rubble
included 10,000 tons of steel and 50,000 cu. yd. of concrete
and masonry.
Implosion instinct
The process was precise, but Anderson admits that it's not
an exact science.
"There are no computer models that can tell you exactly
what will happen," he added. "Experience is the
only way to anticipate the results you'll get."
Although the vast majority of the structure collapsed, the
south wall was intentionally left standing because of its
close proximity to neighboring buildings. That wall will be
brought down this spring by conventional demolition methods.
The project is scheduled for completion in June.
About 90 percent of the structure will be recycled. The
steel will be hauled away and the concrete will be crushed
onsite to help create a subbase for a parking lot on the site.
The site will remain a parking lot until the city determines
how the it will be developed in the future.
A few other sections of walls that were intended to fall
remained standing after the implosion. The added effort to
bring those sections down may weigh on the schedule, but P.K.
Goel, president of Goel Construction Services, said it's a
small price to pay.
"The trade-off is that the more explosive you use to
make sure everything comes down, the more likely you are to
damage things," Goel said. "We're a bit disappointed,
but by the same token it's better than taking the risk."
Anderson said that approximately two dozen windows of neighboring
structures were damaged by the implosion and will be replaced
- a small price compared to the overall project savings.
"If we broke a few windows and that's the sum total
of the damage, that's not too bad," he added. "Implosion
jobs are a wild ride. You get most of what you're looking
for, but not necessarily 100 percent. This is a job where
the whole is greater than the sum of its parts."
Anatomy of an Implosion
|