|
One Step at a Time
Contracting Method Accelerates
and Streamlines the $100 Million Rte. 28
By Tom Gibson
The National Archives and
Records Administration is spending about $110 million over
seven major projects to renovate its National Archives Building
in Washington, D.C.
Once complete in the fall of 2004, the building's occupants
- including theoriginal Declaration of Independence, U.S.
Constitution and Bill of Rights will be better for it.
|
|
|
When deterioration
in the glass encasements holding the Charters of Freedom
documents was discovered in 1997, the National Archives
embarked on a delicate renovation of the rotunda.
|
Marvin Pinkert, director of museum programs at NARA, describes
the building's renovation as a "once-in-a-lifetime experience."
The main thrust is to modernize the 1931-vintage structure
and bring it up to various codes, improve storage conditions
for documents and enhance the experience for people viewing
them.
The first phase of the work - renovating the building's rotunda
and spaces surrounding it - was completed in 2001and reopened
to the public on Sept. 18,Constitution Day.
A second, overlapping phase of renovation will involve completing
work throughout the building, including public spaces, the
theater and research rooms on the ground and basement levels
not associated with the rotunda.
Hartman-Cox Architects of Washington, D.C., serves as the
architect. Grunley Construction of Rockville, Md., a firm
specializing in historic renovation of occupied buildings,
is the general contractor.
Sense of Urgency Planning
for the renovation took on a sense of urgency in 1997 when
deterioration in the glass encasements holding the Charters
of Freedom documents was discovered. These include the Declaration
of Independence, the Constitution and the Bill of
Rights, all displayed to the public in the building's rotunda.
NARA officials determined the Charters of Freedom should
be taken off display for two years starting in July 2001 while
new encasements were constructed for them. Meanwhile, a construction
project to renovate spaces immediately surrounding the rotunda
and those supporting it was accelerated.
The rotunda was previously used for public displays, but
it could hold only a small number of records, and they were
difficult for some people to view.
NARA wanted to dedicate the rotunda fully to the Charters
of Freedom and open up space elsewhere for other attractions,
so three floors of storage area were converted to public museum
areas and exhibit galleries. New entrances, a museum shop
and a research area are located within the new space. Fiber
optic illumination of all the precious documents were designed
and installed by a company that specializes in such work,
Band, Inc., Red Hook, N.Y.
Changing Headroom The building
was originally designed as a records depository, meaning few
people at a time would work in the space. Twenty-one of the
building's floors were only 7 ft.
apart, said Scott Teixeira, project architect for Hartman-Cox
Architects.
The building had a concrete floor every 21 ft. and then two
steel-deck floors at 7 ft. each. "We needed to improve
the headroom, so we removed the lower six 7-ft. floors and
replaced them
with three 14-ft. floors," said Patrick Alexander, project
manager for NARA. Workers replaced the lighter decking floors
with structural steel and concrete to support heavier loads.
"As far as mechanical, electrical and plumbing systems
go, the project saw virtually a complete replacement of all
the systems and components."
Alexander added that to meet the conditions for storage of
the records, "we had to replace all the ductwork and
the complete chiller plant. Before, the best we could do was
about 72 or 73 degrees F and about 52 percent humidity. But
for the long-term life of the records, the
conservationists wanted to get down to 65 degrees and 45 percent
humidity."
The old chillers drew condenser water through two 36-in.
lines from the nearby Tidal Basin. NARA wanted to get off
that system because the water temperature was unpredictable
and the
water dirty, resulting in erratic cooling for the building.
They chose to use cooling towers instead. Crews cut a big
hole in the roof in one corner of the building, took three
floors out and dropped four cooling towers onto the new roof
by crane.
One Complication After Another
"The other complicated piece of the job is we took an
existing parking garage on grade and lowered it 15 or 20 ft.
to make the new 300-seat movie theater, which is underneath
the Constitution Avenue stairs," said Ken Grunley, president
of
Grunley Construction. "A steam line running down Constitution
Avenue used to heat buildings in the federal triangle coursed
through the site, so they had to build a new steam tunnel
under
the sidewalk before they dug out for the theater."
Return
to List
|